On Monday, the Missouri Department
of Transportation announced work starts Monday, August 6 at the
Then on August 13, work will begin
at the U.S. 65 and
The prime contractor on the project is Branco Enterprises of Neosho, doing the work for a low bid amount of $1.3 million.
The whole project is scheduled to be completed by Nov. 30. However, MoDOT says the contractor expects to complete the work by mid-October.
Business 65/St.
Much of the work at the St. James
Street/Business Route 65 intersection will take place at night or when traffic
volumes are lower. Nighttime lane closings will take place between
Drivers can expect traffic shifts on
Business 65 at
When one-lane traffic is needed, flaggers will direct drivers through the work zone.
The St. James/Business 65 project
includes new traffic signals, a new left-turn lane from Business 65 onto
Route 65/Rochester Road
The work on Route 65 at
Drivers can expect lane closings on
both Route 65 and on
Work involves:
* Building U-turn lanes north and
south of the intersection.
* Rebuilding the median crossover to
allow left-turns only. No straight-across traffic will be allowed.
* Installing new highway lighting at
the intersection and at the new U-turn lanes.
* Replacing
rutted pavement on